In order to be able to move individual objects of the landfill to new construction sites, the warehouse of aggregates has serial, easily moved equipment; Concrete mixing node and cement warehouse – prefabricated, with a metal frame. Cement warehouse is four -solid, with a capacity of 75 tons each.
The base of the stand consists of prefabricated reinforced concrete plates with the registers laid in them for heating, as well as covers, caps and other portable elements. The equipment of the boiler room can easily understand and move. This requires reliable equipment, such as a welding inverter.
The duration of the entire technological cycle in summer-24 hours, in winter-48 hours.
Lifting and transport operations for the supply of concrete mixture, removing finished products from the stand and transferring them to the warehouse, as well as loading for transport are performed for a stand with an annual performance of 5 thousand. m autocrane with a carrying capacity of 10 g and for a stand with a capacity of 10 thousand. M3 per year with a tower crane with a lifting capacity of 5 tons with an arrival of an arrow of 22 m or a goat crane with a span of 35 m with consoles of 7 g with a lifting capacity of 5 tons. The supply of concrete, reinforcement and on -boards to the stands of the stand is carried out by a carrier.
The concrete mixing node consists of two sections, one of which (for heavy concrete) is equipped with concrete mixers with a capacity of 250 and 100 liters for polygons with an annual capacity of 5 thousand..I3 and (respectively) 450 and 250 liters for landfills with a capacity of 10 thousand. M3; The second section (for light concrete and solutions) is equipped with two 325 liter solutions for a landfill with a capacity of 5 thousand. mg and two solutions of 750 liters for a polygon with a capacity of 10 thousand. M3.